How Much Secondary Containment Does a Fertigation Tank Need?
There is no universal 110 percent rule. This guide runs the screening arithmetic for one tank, A/B pairs and transfer pads, then lists the checks that decide whether a spill pallet actually complies.

Disclosure: We may earn a commission if you purchase through links on this page, at no additional cost to you.
A sizing and acceptance guide for stock tanks, IBCs and mixing stations
There is no universal 110 percent rule for every fertigation site. The correct containment volume depends on the local rule or design basis, the largest primary tank, other equipment inside the bund, rainfall or freeboard requirements, and whether the area is a single stock tank, an A/B station or a transfer pad. Greenhouse guidance recommends secondary containment for fertilizer stock tanks and cites 125 percent for a large bulk container, while other agricultural guidance uses 110 to 125 percent plus displacement. Treat the percentage as a starting design criterion, not a substitute for the governing requirement.
This guide answers a practical buying question: how do you turn a 1,000 L tank or IBC specification into a containment requirement that can be checked against a spill pallet, bund, curb or lined pad? It separates screening arithmetic from legal compliance, then shows what must be verified before a supplier's "spill pallet" or "secondary containment" wording is accepted.
The first number to write down is usable capacity
A containment system is sized by its usable liquid volume, not by the outside footprint of the tray or the height of its wall. Grating, tank bases, support legs, pump skids and other objects can displace volume. A drain, open doorway or permeable floor can reduce the system's real ability to keep fertilizer away from soil and water. Ask for the manufacturer's net sump or containment capacity and the assumptions behind it.
| Term | What it means in a procurement review | Why it matters |
|---|---|---|
| Primary volume | The maximum liquid volume in the largest tank, IBC or vessel that the containment is intended to protect | This is the release scenario used by many rules and design guides |
| Net containment capacity | The liquid volume available below the overflow or wall after the grate, tank supports and fixed equipment are accounted for | A large-looking pallet can still fail the required volume test |
| Displacement | The volume occupied by other tanks, bases, pumps, pipe supports or equipment inside the containment | Some rules explicitly require this volume to be added to the design basis |
| Rain or freeboard allowance | Additional capacity or a covered arrangement for precipitation and emergency water where the local rule requires it | Outdoor bunds can lose usable capacity to clean rainwater before a fertilizer release occurs |
Do not use gross dimensions to calculate a product's sump volume unless the supplier provides a validated calculation. A 1,300 mm by 1,300 mm pallet is a footprint; it is not proof of 1,100 L, 1,250 L or any other net capacity.
Which design basis applies
| Source or jurisdiction | Published signal | How to use it |
|---|---|---|
| Greenhouse best-management guidance | Use secondary containment routinely for fertilizer stock tanks; large bulk-tank areas should contain 125 percent of the largest bulk container | A conservative screening basis when a more specific local rule is not yet confirmed |
| Pesticide and mixing-facility guidance | Containment should hold 110 to 125 percent of the largest tank plus the volume displaced by other tanks in the area | Use the percentage and displacement together; do not compare only the largest-tank percentage |
| Regional fertigation guidance (example: Environment Canterbury) | For storage installations of 1,001 L and greater, established good practice is bunding for at least 110 percent of the largest tank, with impervious containment and recovery access | A useful example of a fertigation-specific threshold, not a universal international rule |
| Chemigation safety guidance (example: Minnesota) | The stated minimum is 125 percent, or 110 percent when the unit is under a roof, with additional conditions based on tank size, water proximity and storage duration | Check the whole local rule, including site triggers and construction materials |
| State and local bulk-fertilizer rules | Examples such as Washington and Michigan use thresholds, tank-size triggers, rain allowances or specific construction requirements | The legal answer is location- and substance-specific; ask the authority or a qualified designer before ordering a containment system |
These sources do not conflict simply because their percentages differ. They address different substances, site conditions and regulatory frameworks. An article or supplier page that states "110 percent compliant" without naming the jurisdiction, stored liquid, precipitation treatment and test basis is incomplete.
Run the calculation before you compare products
Use the following as a screening worksheet. The final design basis must come from the applicable rule, permit, insurer, engineer or environmental authority. Record the result in litres and gallons if the site uses both systems.
| Scenario | 110 percent screening value | 125 percent screening value | What still has to be added or checked |
|---|---|---|---|
| One 1,000 L stock tank | 1,100 L net containment | 1,250 L net containment | Displacement, rain or freeboard, tank anchoring and local threshold |
| Two 1,000 L A/B tanks | At least 1,100 L for the largest release under a largest-tank rule, plus displacement and any local aggregate requirement | At least 1,250 L for the largest release under a largest-tank rule, plus displacement and any local aggregate requirement | Whether the rule treats both tanks as one storage system, plus separation, shared drainage and access |
| One 500 L stock tank plus a 100 L transfer container | 550 L before displacement or site allowances under a 110 percent largest-tank basis | 625 L before displacement or site allowances under a 125 percent largest-tank basis | Transfer hose spill volume, pump skid, container placement and whether the transfer pad is a separate containment area |
For two tanks, do not quietly add 110 percent of both tanks unless the governing rule says to use aggregate volume. Equally, do not assume that 110 percent of the largest tank is sufficient everywhere. The correct question is: what release scenario and what site-specific additions does the rule require?
A/B tanks change the layout as well as the volume
A/B fertigation systems often keep calcium-containing stock separate from phosphate or sulfate concentrates until injection. That chemistry decision creates a containment decision: both tanks, their valves, the transfer point and any shared pump or manifold may need to sit inside the same impermeable boundary, or in separate cells that prevent an incompatible spill from mixing. The containment volume is only one part of the risk assessment.
| Layout question | Buyer action |
|---|---|
| Can one tank's failure reach the other tank? | Set the tank spacing, curb height and partition arrangement so a release does not create an avoidable A/B mixing event |
| Where do the valves and hoses sit? | Keep the lowest valves, hose connections and transfer points inside the containment footprint; do not place the primary tank inside a bund while its valve projects outside it |
| Can the operator remove contaminated liquid? | Provide a controlled recovery point or pump-out method; a drain that goes to soil, stormwater or an unprotected floor is not a spill plan |
| Will rain enter the area? | Use a roof or calculate the required rain allowance; never rely on an unverified open drain to remove clean water from a chemically contaminated bund |
The failure modes that make a nominally adequate bund fail
| Failure mode | What the buyer should inspect |
|---|---|
| The sump is smaller than the label implies | Request net capacity, a drawing and the capacity with grate and tank supports installed |
| The floor or liner leaks | Confirm an impermeable, chemically compatible base and inspect seams, penetrations and wall-to-floor joints |
| A drain is left open | Use a normally closed, controlled recovery arrangement; a drain must not discharge fertilizer to soil, a storm drain or an unprotected sewer |
| The tank floats or shifts | Check anchoring, support and buoyancy for the case where the containment fills with water or released liquid |
| Rainwater consumes capacity | Keep the bund covered where practical, or include the required precipitation and freeboard volume plus a documented clean-water removal procedure |
| The transfer pad is outside the bund | Treat filling, hose disconnection and pump maintenance as spill points and provide a separate impermeable mix and load pad if needed |
Secondary containment is not a substitute for a sound primary tank. Extension guidance frames a solid, impermeable floor, prompt cleanup and accessible spill equipment as part of the storage system. The containment boundary should make a failure recoverable; it should not make routine small leaks invisible.
Sourcing candidates for a containment review
These listings are sourcing candidates for an inquiry, not approved compliance equipment. Marketplace fields are supplier or platform statements and do not establish net sump capacity, chemical compatibility or the delivered configuration.
RFQ wording for a containment supplier
Please quote secondary containment for [number] fertilizer tank(s) with a largest primary volume of [L] and a maximum stored specific gravity of [value]. State the net usable containment capacity with grating, tank supports and fixed equipment installed; design percentage and governing standard; displacement allowance; precipitation and freeboard basis; liner or polymer material and chemical-compatibility statement; wall and floor construction; drain or pump-out arrangement; overflow or high-level control; tank anchoring; access and recovery method; delivered dimensions; load rating; UV exposure; temperature range; drawing revision; MOQ; lead time; warranty and replacement parts. Confirm whether the quote covers the tank, pallet, grate, drain, cover and any transfer pad as one system or as separate items.
Acceptance check before filling the tank
| Check | Pass condition |
|---|---|
| Design basis | The supplier quote names the applicable percentage, standard or local requirement and does not rely on a generic "110 percent" badge |
| Net volume | The measured or documented usable sump capacity meets the required volume after grating, supports and equipment displacement |
| Impermeability | The floor, liner, seams, penetrations and wall joints are intact and chemically suitable for the fertilizer and cleaning solution |
| Drain control | Any drain is normally closed or routed to a controlled recovery point; it cannot discharge contaminated liquid to soil or stormwater |
| Layout | The primary tank, valves, hoses, transfer point and pump skid are inside the intended containment boundary |
| Stability | The tank is supported and anchored for the filled and spill-filled conditions; pipework does not impose damaging loads on the tank or liner |
| Response | Labels, inventory, inspection frequency, absorbent or recovery equipment and an incident procedure are available to the operators |
If the supplier cannot provide net capacity, material compatibility and a drawing, keep the offer at inquiry status. A low-price tray can still be useful as a drip-control accessory, but it should not be described as full secondary containment for a 1,000 L fertilizer tank.
Bottom line
Start with the local design basis, then calculate from the largest credible release and the actual usable sump capacity. For a 1,000 L tank, 1,100 L is the arithmetic result at 110 percent and 1,250 L at 125 percent, before any required displacement, rain or freeboard allowance. A/B systems require a layout and compatibility review in addition to volume. Product pages are useful for discovery, but the purchase decision should wait for a drawing, a net-capacity statement, chemical-compatibility evidence and a controlled recovery plan.
Share this article